Panels on Park View Mennonite Church

The solar installation at Park View Mennonite Church was completed Friday afternoon – November 9. The 75 solar PV panels took three days to install and will be up and running soon! Below are a few pictures documenting our progress – keep checking our blog for updates!

Wednesday, Nov. 7th

Got Electric, LLC setting the racking system – the racking system will hold 75 panels on the church roof

 

 

 

 

 

 

 

 

 

Thursday, Nov. 8th:

A cold morning, but we’re heating up the roof!!

 

 

 

 

 

 

 

 

Placing the inverters and dealing with the electrical wires to get ready for the PV panels

 

 

 

 

 

 

 

 

 

 

Friday, Nov. 9th:

 

 

 

 

 

 

 

View from College Ave.

 

 

 

 

 

 

 

 

 

 
The church now holds 125 panels including the 75 installed this past week. We will continue to update our followers once the panels are up and running!


Written by: Tony Smith

Categorized:

Tagged: